Monthly Archives: February 2018

Can Retainage Be Held Until Final Completion Of The Project?

February 6th, 2018 (No Comments)

On public projects, an owner typically withholds retainage of 10%. Can the owner hold this 10% retainage until final completion? The short answer is, No! Section 3921 of the PA Procurement Code mandates that, when the contract is 50% completed, retainage “shall not exceed 5% of the value of completed work” and can then be withheld only […]